Hubbell Goes Extreme for Anawim Housing Project - 9 homes in 9 days

Project Schedule

Daily Breakout
Wednesday, September 9

  • Braveheart Scene (9 a.m.)
  • Walls set up on 1st floor  (9 a.m. to 1 p.m.)
  • Crane setting 2nd Floor Decking (11 a.m. to 1 p.m.)
  • 2nd floor wall setting (1 p.m. to 1 a.m.)

Thursday, September 10

  • Set roof trusses (6 a.m. to 6 p.m.)
  • Roofing process (all day)
  • Tyvek wrapping of house (4 p.m. to 10 p.m.)

Friday, September 11

  • Window Delivery (5 a.m. to 8 a.m.)
  • Window installation (6 a.m. to 1 p.m.)
  • Roof shingle installation (6 a.m. to 4 p.m.)
  • Siding installation (1 p.m. to 4 a.m.)
  • HVAC, Plumbing, Electrical, phone/data rough in (8 a.m. to 8 p.m.)

Saturday, September 12

  • Insulation Inspection (8 a.m. to 11 a.m.)
  • Energy Inspection (4 p.m. to 7 p.m.)
  • Drywall hang, finish, texture (12 p.m. to 8 p.m.)
  • Sidewalk pouring (start at 10 a.m.)

Sunday, September 13

  • Drywall finishing (all day)

Monday, September 14

  • Prime and Paint interior (2 a.m. to 11 a.m.)
  • Deliver and install cabinets and counters (9 a.m. to 12 a.m.)
  • Landscaping (2 p.m. to 10 p.m.)

Tuesday, September 15

  • Electrical, Plumbing, phone/date trim (4 a.m. to 4 p.m.)
  • Install closet shelving (1 p.m. to 4 p.m.)
  • Install carpet and flooring (7 p.m. Tuesday to 7 p.m. Wednesday)

Wednesday, September 16

  • Install carpet and flooring (until 7 p.m.)
  • Appliance delivery and installation (4 p.m. to 1 a.m.)
  • Install doors, hardware, blinds (11 a.m. to 10 p.m.)
  • Mirror installation (7 p.m. to 10 p.m.)

Friday, September 18

  • Reveal to families at 3 p.m.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 