Project Schedule
Daily Breakout
Wednesday, September 9
- Braveheart Scene (9 a.m.)
- Walls set up on 1st floor (9 a.m. to 1 p.m.)
- Crane setting 2nd Floor Decking (11 a.m. to 1 p.m.)
- 2nd floor wall setting (1 p.m. to 1 a.m.)
Thursday, September 10
- Set roof trusses (6 a.m. to 6 p.m.)
- Roofing process (all day)
- Tyvek wrapping of house (4 p.m. to 10 p.m.)
Friday, September 11
- Window Delivery (5 a.m. to 8 a.m.)
- Window installation (6 a.m. to 1 p.m.)
- Roof shingle installation (6 a.m. to 4 p.m.)
- Siding installation (1 p.m. to 4 a.m.)
- HVAC, Plumbing, Electrical, phone/data rough in (8 a.m. to 8 p.m.)
Saturday, September 12
- Insulation Inspection (8 a.m. to 11 a.m.)
- Energy Inspection (4 p.m. to 7 p.m.)
- Drywall hang, finish, texture (12 p.m. to 8 p.m.)
- Sidewalk pouring (start at 10 a.m.)
Sunday, September 13
- Drywall finishing (all day)
Monday, September 14
- Prime and Paint interior (2 a.m. to 11 a.m.)
- Deliver and install cabinets and counters (9 a.m. to 12 a.m.)
- Landscaping (2 p.m. to 10 p.m.)
Tuesday, September 15
- Electrical, Plumbing, phone/date trim (4 a.m. to 4 p.m.)
- Install closet shelving (1 p.m. to 4 p.m.)
- Install carpet and flooring (7 p.m. Tuesday to 7 p.m. Wednesday)
Wednesday, September 16
- Install carpet and flooring (until 7 p.m.)
- Appliance delivery and installation (4 p.m. to 1 a.m.)
- Install doors, hardware, blinds (11 a.m. to 10 p.m.)
- Mirror installation (7 p.m. to 10 p.m.)
Friday, September 18
- Reveal to families at 3 p.m.